Which product, when produced, defines the way a project is to be delivered after evaluating various delivery methods?

  1. Project Charter

  2. Project Brief

  3. Project approach

  4. Project Plan

The correct answer is: Project approach

The product that defines the way a project is to be delivered after evaluating various delivery methods is the project approach. This document provides a structured outline of how the project will be delivered, detailing the selected methods and processes based on an assessment of alternatives. It serves as a guide that informs stakeholders about the choices made regarding project execution, ensuring that everyone has a clear understanding of the rationale behind the selected delivery mechanism. The project charter primarily establishes the project's existence and outlines its objectives and stakeholders but does not specify delivery methodology. The project brief consists of higher-level information about the project's scope and purpose without delving deeply into delivery methods. The project plan, while crucial in detailing the execution, timelines, and resources of the project, follows the project approach; it is created after the delivery method has been determined. Thus, the project approach is pivotal in transitioning from the conceptual phase to practical implementation, making it the correct answer.