Which of the following activities would be carried out during the Starting Up a Project process?

  1. Finalize project budget

  2. Appoint individuals to carry out work required in project initiation

  3. Create a communication plan

  4. Conduct a stakeholder analysis

The correct answer is: Appoint individuals to carry out work required in project initiation

During the Starting Up a Project process in PRINCE2, one of the key activities is appointing individuals who will carry out the work necessary for project initiation. This step is essential because it ensures that the right people are in place to develop the project brief and complete the necessary outlines that set the foundation for the project. By identifying and appointing team members who will contribute to the project initiation, the organization ensures that there are adequate resources and expertise directed toward defining the project's objectives, scope, and risks. While finalizing the project budget, creating a communication plan, and conducting a stakeholder analysis are important activities in the overall project management process, they are not typically tasks that occur specifically during the Starting Up a Project phase. Instead, these activities are more aligned with the later stages of project planning and execution, where detailed budgeting, stakeholder engagement, and communication strategies are fully developed. The Starting Up a Project phase primarily focuses on assembling the team needed to establish a solid project structure and framework, laying the groundwork for subsequent planning and delivery phases.